From: A novel approach of a dynamic multi objective optimization of a power distribution system
Maximum active power available from the source: 4000Â kW | |||
---|---|---|---|
Maximum reactive power available from the source: 3500 kVAr | |||
 | Without reconfiguration | After reconfiguration | Reduction (%) |
Total active power load (kW) | 2967.0 | 2967.0 | 0 |
Total reactive power load (kVAr) | 2555.0 | 2555.0 | 0 |
Open switches | S69, S70, S71, S72, S73 | S14, S57, S61, S69, S70 | / |
Active power losses (kW) | 102.58 | 93.85 | 8.51 |
Reactive power losses (kVAr) | 56.148 | 52.285 | 6.88 |
Vmin (p.u.) | 0.9744 (node 17) | 0.9766 (node 14) | / |
Vde (p.u.) | 0.0256 | 0.0234 | 8.59 |
Supplied node | 1 to 69 | 1 to 69 | / |
SAIFI (failure/day) | 0 | 0 | / |
SAIDI (h/day) | 0 | 0 | / |